Proposal to replace 23 aging stream crossing structures within the Forest Service road and trail systems. Two of the sites are replacements or rehabilitation of road bridges. The other 21 sites are replacements of culverts.
Location
23 locations across the National Forest
Project timeline
1
Scoping Start
01/14/2022
2
Decision
05/2022 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| 2022 Forest Wide Watershed Improvement Project | Decision Signed Date: 05/12/2022 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Medford-Park Falls Ranger District; Great Divide Ranger District; Eagle River-Florence Ranger District; Lakewood-Laona Ranger District; Washburn Ranger District |
| Legal Land Description | Not Applicable |