Restore trails in the Namakagon Cluster of the CAMBA mountain bike trail system to the sustainable standards to which they were originally constructed and reroute some sections from timber sale haul routes to single-track routes.
Location
CAMBA Mountain Bike Trail System - Namakagon Cluster
Project timeline
1
Scoping Start
01/05/2022
2
Decision
08/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Chequamegon Area Mountain Bike Association Trail Maintenance, Rehab and Reroutes - Namekagon Cluster | Decision Signed Date: 08/23/2023 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Great Divide Ranger District |
| Legal Land Description | Not Applicable |