Clark Electric is proposing to convert 11,280 feet of overhead utility line to underground along FR 119. The conversion will take place in Clark Electric's current right of way. One segment will be relocated from Lake Marion to the 119 right of way.
Location
The project will take place between FR 554 and FR 121 in the existing right of way of FR 119.
Project timeline
1
Scoping Start
05/01/2024
2
Decision
07/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Clark Electric Overhead Conversion 2024 | Decision Signed Date: 07/24/2024 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Medford-Park Falls Ranger District |