The purpose of this project is to reroute a section of trail that continuously gets flooded in the spring. There would be new trail construction of approximately 1 mile in length and 2-3 feet in width.
Location
North of State Hwy 70 E and west of Forest Road 2150 near Perch Lake.
Project timeline
1
Scoping Start
03/24/2025
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| 2025 Perch Lake Trail Reroute | Decision Signed Date: 05/06/2025 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | T40N R16E Section 20 and 21 |