GLGT is requesting to conduct a federally mandated integrity dig. Routine inspections detected anomalies along pipe segments that may require maintenance. The dig will provide visual inspection and the ability to perform required maintenance. The work will be conducted on Line 100.
Location
South of Highway 2, East of Bena
Project timeline
1
NEPA Start Date
12/1/2025
2
Finding/Decision Date
12/11/2025
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |