Use an adaptive management driven multi-agency approach to 1) Prevent the further spread of NNIP 2). Prevent and reduce impacts from existing NNIP infestations in the area. 3). Restore the land's resistance to NNIP
Location
Forest-wide
Project timeline
1
Scoping Start
05/14/2008
2
Comment Period
07/10/2011
3
Decision
10/2011 (Estimated)
4
Implementation
06/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Noxious Weed Treatments |
| Non-native Invasive Plant Management | Decision Signed Date: 10/03/2011 Legal Notice Date: 10/11/2011 |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |