The supporting analysis for the proposed installation of a street light located in Cass County at CR 9 and US Hwy 2; and the proposed rerouting of underground electric cable in Itasca County along CR 49 in Section 27, T58N R25W
Location
Cass County at CR 9 and US Hwy 2; Itasca County along CR 49 in Section 27, T58N R25W
Project timeline
1
Scoping Start
04/19/2012
2
Comment Period
04/26/2012
3
Decision
06/2012 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Lake Country Power Project | Decision Signed Date: 06/04/2012 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |