Construction of an elevated 4-foot-wide boardwalk trail (221 feet long) that connects to another trail on the bog loop in the wetland. The boardwalk is adjacent to a new wayside rest area on the Lady Slipper Scenic Byway.
Location
Beltrami County, near Pennington, T147N, R30W, Section 33
Project timeline
1
Scoping Start
05/19/2013
2
Comment Period
05/19/2013
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)