Construct 3 passing lanes, several turn lanes, and thin stands on south side of Highway 2 from Cass Lake to Ball Club to improve safety conditions. FS to issue easement along Hwy 2 corridor to MnDOT.
Location
Highway 2 between Cass Lake and Deer River. Project is within Leech Lake Reservation.
Project timeline
1
Scoping Start
01/28/2014
2
Comment Period
05/13/2014
3
Objection Period Start
06/28/2014
4
Decision
08/2014 (Estimated)
5
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Improvements/Construction |
| Trunk Highway 2 Corridor Improvement Project | Decision Signed Date: 08/25/2014 |
| Forests | Chippewa National Forest |
| Districts | Chippewa National Forest All Units |
| Legal Land Description | Not Applicable |