Cabin owner is prposing to build a 20' x 20' garage.
Location
Project will take place on Lot 6 of the North Sioux Summer Home group. These units are on the northeast side of Cut Foot Sioux Lake.
Project timeline
1
Scoping Start
05/05/2014
2
Decision
05/2014 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| North sioux Lot 6 Summer Home Garage Project | Decision Signed Date: 05/29/2014 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T147N R27W Sec 22 5th PM |