Decision Memo Completed

Enbridge Permit Reauthorization

Chippewa National Forest Cass; Itasca, Minnesota Chippewa National Forest All Units

New term permit authorization of Enbridge Pipeline Permit CAL401902 which expired 12/31/17.

Location

Crosses through the middle of the Forest; generally parallel to Hwy 2. On the Leech Lake Reservation.

Project timeline

1
Scoping Start
03/17/2017
2
Decision
05/2020 (Estimated)
3
Implementation
08/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Enbridge Permit ReauthorizationDecision Signed Date: 05/22/2020
ForestsChippewa National Forest
DistrictsChippewa National Forest All Units
Legal Land DescriptionNot Applicable
Special use management