Decision Memo Completed

Lake Country Power Amendment 14

Chippewa National Forest Itasca, Minnesota Deer River Ranger District

Amend an existing permit to install approx. 1496 feet of underground power line 5 to 10 feet off the north side of Doan Lake Road to serve existing customers. Project is not within the Leech Lake Band of Ojibwe Reservation boundary.

Location

Project is located in Wabana Township

Project timeline

1
Scoping Start
11/23/2016
2
Decision
02/2017 (Estimated)
3
Implementation
03/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Lake Country Power Amendment 14Decision Signed Date: 02/22/2017
ForestsChippewa National Forest
DistrictsDeer River Ranger District
Legal Land DescriptionT57N, R25W, S18, W1/2SE1/4
Special use management