Reconstruction of a 15.6-mile segment of TH 200, an existing two-lane from MN 371 to MN 84. Roadway work includes repair/replacement of bridge 8136 over Cedar Creek and bridge 8533 over Bag Creek. FS would issue new 100' easement.
Location
Highway 200 between MN 371 and MN 84. Project is within Leech Lake Band of Ojibwe Reservation
Project timeline
1
Scoping Start
05/21/2018
2
Decision
09/2020 (Estimated)
3
Implementation
12/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Trunk Highway (TH) 200 Improvement Project | Decision Signed Date: 09/22/2020 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | Not Applicable |