Upgrade existing copper lines with installation of fiber optic in the existing right of way to comply with FCC requirements and meet customer demands for broadband. Within LLBO boundary
Location
Norway Beach-Pike Bay and Pennington Area
Project timeline
1
Scoping Start
08/13/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Paul Bunyan Fiber Optic Cable BLD401201 Amendment 17 | Decision Signed Date: 10/07/2020 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |