Installation and maintenance of 2558 feet of fiber optic communications cable. Installation and maintenance of BD5 pedestals and 24 x 36 inch vaults
Location
North of Turtle Lake
Project timeline
1
Scoping Start
07/01/2021
2
Decision
07/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Becker Rd Arvig Amend 7 | Decision Signed Date: 07/14/2021 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T60N, R26W, Section 31 |