Installation and maintenance of pedestals and 2640%u2019 of fiber optic communication cable in the ROW of FR2158 aka County Highway 262. Vibrational plow will be used except where noted, then directional bore will be the installation method.
Location
West of Little North Star Lake
Project timeline
1
Scoping Start
04/01/2022
2
Decision
05/2022 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| FR2158 Arvig Amend 6 | Decision Signed Date: 05/20/2022 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T59N, R26W, Sec 19, 30 |