Decision Memo Completed

Blackduck Ranger Station Updates

Chippewa National Forest Beltrami, Minnesota Chippewa National Forest All Units

Decommisioning and disposal of the existing North and south warehouses, oil shed, and pesticide shed at the Blackduck Ranger Station and the construction of new buildings as replacements.

Location

BlackDuck Ranger Station

Project timeline

1
Scoping Start
12/06/2022
2
Decision
02/2023 (Estimated)
3
Implementation
05/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Blackduck Ranger Station UpdatesDecision Signed Date: 02/07/2023
ForestsChippewa National Forest
DistrictsBlackduck Ranger District
Legal Land DescriptionT149N R31W Sec 13