Decommisioning and disposal of the existing North and south warehouses, oil shed, and pesticide shed at the Blackduck Ranger Station and the construction of new buildings as replacements.
Location
BlackDuck Ranger Station
Project timeline
1
Scoping Start
12/06/2022
2
Decision
02/2023 (Estimated)
3
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Blackduck Ranger Station Updates | Decision Signed Date: 02/07/2023 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T149N R31W Sec 13 |