Installation and maintenance of fiber optic distribution lines in existing corridor for 25,000 feet. Will use direct burial plowing methods and low impact direction drilling will be used for crossing all streams and roads.
Location
Boy River/Remer area
Project timeline
1
Scoping Start
06/21/2023
2
Decision
10/2023 (Estimated)
3
Implementation
11/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Johnson Telephone Company Amendment 10 | Decision Signed Date: 10/23/2023 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District; Walker Ranger District |
| Legal Land Description | T142N, R26W, Sec. 21, 27, and 28 & T143N, R25W, Sec.18 & T143N R26W, Sec. 13, 22, 27, and 34 |