Installation and maintenance of 50,702 ft of line using a vibratory plow or directional bore under road and water ways. Segments of the line are pre-existing and whole line will be upgraded. Construction planned in 2024.
Location
In the Bigfork Area
Project timeline
1
Scoping Start
08/14/2023
2
Decision
02/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| People's - Amendment 12 Bigfork | Decision Signed Date: 02/22/2024 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | Not Applicable |