Installation of a new service feed by 500ft directional bore and then south 70ft of bore to current meter location. Install of a new cable 120ft directional bored east to FS communication equipment. Clearing and installing new cabinets in ROWs.
Location
Northern Research Center & FS Communication Site (Locations are approximately 700%u2019 apart from each other on FR2143/Wilderness Trail)
Project timeline
1
Scoping Start
09/21/2023
2
Decision
10/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lake Country Power - Amendment 29 | Decision Signed Date: 10/04/2023 |
| Forests | Chippewa National Forest |
| Districts | Deer River Ranger District |
| Legal Land Description | T58N, R25W, Sec. 11 & 14 |