Improve accessibility of site that is utilized for a sugar bush by the Addiction and Dependency program. The improvements will be to construct a pavilion and stairs with a handrails.
Location
Between Cass Lake and Big Lake Between Cass Lake and Big Lake Between Cass Lake and Big Lake
Project timeline
1
Scoping Start
09/15/2023
2
Decision
09/2023 (Estimated)
3
Implementation
11/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sugarbush Project | Decision Signed Date: 09/27/2023 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | Not Applicable |