Dredge the Harbor and deposit dredge material on FS land. The deposit location for the dredging material is the same as a previous dredging project
Location
Stony Point on Leech Lake
Project timeline
1
Scoping Start
10/05/2023
2
Decision
11/2023 (Estimated)
3
Implementation
12/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Harbor Dredging of Stony Point | Decision Signed Date: 11/08/2023 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T142N, R30W, Section 10 |