Decision Memo Completed

CSAH 53 Bridge Replacement

Chippewa National Forest Cass, Minnesota Chippewa National Forest All Units

Replacing a bridge on CSAH 53 aprox 9 miles northwest of Remer, MN

Location

Approximately 9 miles Northwest of Remer, MN on Tobique Road NE at Boy River Bridge

Project timeline

1
Scoping Start
02/21/2024
2
Decision
05/2024 (Estimated)
3
Implementation
06/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction
CSAH 53 Bridge ReplacementDecision Signed Date: 05/28/2024
ForestsChippewa National Forest
DistrictsWalker Ranger District
Legal Land DescriptionT142N, R27W, Sec. 33
Road management