Culverts on the trail have raised out of the ground high enough that mowers are not able to progress on the trail. replacement of the culverts lower in the ground will fix the issue and puncheon would be built over the gap
Location
Lat: 47.127323 Long: -93.921931 Township 54, Range 26, Section 11
Project timeline
1
Scoping Start
04/26/2024
2
Decision
01/1970 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Decision Decided Date | 07/02/2026 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |