Installation and maintenance of 972 feet of line to be installed in a 36-inch-wide corridor to reach a residence. Trees will be cleared along the corridor route. This project is outside of the reservation boundary.
Location
Howard Lake Area
Project timeline
1
Scoping Start
01/24/2025
2
Decision
03/2025 (Estimated)
3
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Itasca Mantrap Amendment 6- Howard Lake Area | Decision Signed Date: 03/04/2025 |
| Forests | Chippewa National Forest |
| Districts | Walker Ranger District |
| Legal Land Description | T141N, R31W, Section 31 |