Re-issue Special Use Permit to authorize all existing Green Mountain Power (GMP) power lines located across the Forest and to authorize transfer of permit from Central Vermont Public Service (CVPS).
Location
Green Mountain National Forest, multiple towns
Project timeline
1
Scoping Start
09/25/2017
2
Decision
09/2018 (Estimated)
3
Implementation
10/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10); 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Green Mountain Power (formerly CVPS) Special Use Permit Renewal | Decision Signed Date: 09/11/2018 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Green Mountain And Finger Lakes National Forest All Units |
| Legal Land Description | Multiple counties and towns. |