Increase the size of the existing parking lot along VT Route 100 to provide a safe access for Warren Falls.
Location
Town of Warren
Project timeline
1
Scoping Start
06/05/2012
2
Comment Period
06/05/2012
3
Decision
09/2012 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Trail Management |
| Warren Falls Parking Lot Expansion Project | Decision Signed Date: 09/18/2012 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |