Reconstruct approximately 300 foot section of the Hogback Trail within the Blueberry Hill Nordic trail system. Includes repair of a drainage ditch and trail tread, installation of 5 new culverts, and replacement of an existing culvert.
Location
Town of Goshen
Project timeline
1
Scoping Start
11/20/2012
2
Comment Period
11/20/2012
3
Decision
04/2013 (Estimated)
4
Implementation
05/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Blueberry Hill Hogback Mountain Loop Trail Project | Decision Signed Date: 04/17/2013 |
| Forests | Green Mountain And Finger Lakes National Forests |