Relocate a 750 foot section of Appalachian Trail (AT) from private land to federal land in the Town of Pomfret.
Location
Town of Pomfret
Project timeline
1
Scoping Start
04/02/2013
2
Comment Period
04/02/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Appalachian Trail Pomfret Relocation | Decision Signed Date: 06/03/2013 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |