Install a new communication line in a trench that would upgrade chairlift safety switches, and telephone and electronic lines. Includes the removal of selected trees to provide a safer approach. Decision Memo not needed due to scope of the project.
Location
Town of Warren.
Project timeline
1
Scoping Start
04/2014 (Estimated)
2
Decision
06/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |
| Legal Land Description | Not Applicable |