Remove existing bridge from Elsie's Loop Trail and move it intact to a the Sucker Brook #1 location. The analysis at this level was cancelled because the project fit a category not requiring a Decision Memo.
Location
Town of Goshen.
Project timeline
1
Scoping Start
07/15/2016
2
Decision
12/2016 (Estimated)
3
Implementation
06/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |