Decision Memo Completed

Hapgood Nature Trail Improvements

Green Mountain and Finger Lakes National Forests Bennington, Vermont Manchester Ranger District

Remove three bridges, build one new bridge, and construct two separate short sections of trail reroute along the existing nature trail.

Location

Town of Peru

Project timeline

1
Scoping Start
10/27/2014
2
Decision
07/2015 (Estimated)
3
Implementation
10/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management; Watershed Improvements
Hapgood Nature Trail ProjectDecision Signed Date: 07/22/2015
ForestsGreen Mountain And Finger Lakes National Forests
DistrictsManchester Ranger District
Legal Land DescriptionNot Applicable
Recreation management