Construct 800 foot access road, trailhead parking and add existing trail to NFS system. Decision Memo cancelled because the proposal will now be included in the Somerset integrated resource project with scoping anticipated in late 2018.
Location
Town of Dover
Project timeline
1
Scoping Start
02/22/2017
2
Decision
10/2017 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Road Improvements/Construction |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |