Installation of 4 utility poles and 1,180 feet of powerline to bring power to private parcels in the Towns of Readsboro and Woodford; Reconstruction of 2 utility poles and approx. 300 feet of powerline in the Town of Bristol.
Location
Towns of Readsboro, Woodford, Bristol, Vermont
Project timeline
1
Scoping Start
06/16/2017
2
Decision
08/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Green Mountain Power 2017 Construction/Reconstruction Special Use Permits | Decision Signed Date: 08/14/2017 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District; Manchester Ranger District |
| Legal Land Description | Not Applicable |