Two sections of Sleeper Trail would be widened between 20-40 feet in order to meet intermediate level standards totaling 0.40 acres. Trees would be removed, stumps pulled and final grading. Blasting not anticipated, but may be necessary in locations.
Location
Town of Warren.
Project timeline
1
Scoping Start
04/10/2018
2
Decision
11/2018 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sugarbush Sleeper Trail Widening | Decision Signed Date: 11/26/2018 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |
| Legal Land Description | Not Applicable |