Green Mountain Power proposes to reconstruct a power line on VT Route 125 in Ripton, with 5 foot taller poles & covered conductors, under the authority of a Special Use Permit. 808 feet of the line crosses National Forest Lands.
Location
Town of Ripton
Project timeline
1
Scoping Start
12/17/2018
2
Decision
12/2018 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Green Mountain Power Route 125 Power Line Reconstruction Special Use | Decision Signed Date: 12/17/2018 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |