Project timeline
1
Scoping Start
02/15/2019
2
Decision
02/2019 (Estimated)
3
Implementation
02/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Hector Half-Hundred Permit Reissuance | Decision Signed Date: 02/15/2019 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Hector Ranger District |
| Legal Land Description | Not Applicable |