The project would consist of the issuance of a road right-of-way permit to Mr. Smith for the reconstruction, utilization, and maintenance of a timber haul road and a gate. The road would be 16 feet wide and 0.46 miles long, covering 0.89 acres.
Location
Town of Ripton
Project timeline
1
Scoping Start
04/24/2019
2
Decision
07/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Smith ROW Authorization | Decision Signed Date: 07/24/2019 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |