A permit with a two year term would be issued to Green Mountain Power for construction of an underground powerline from an existing pole on Little Pond Road (Forest Road 275) and install approximately 600 feet of conduit.
Location
Town of Woodford
Project timeline
1
Scoping Start
12/06/2019
2
Decision
02/2020 (Estimated)
3
Implementation
07/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| GMP Little Pond Road Electric Line Construction Permit | Decision Signed Date: 02/24/2020 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |