This project consists of large wood placement on approximately 2.1 miles of stream along the South Fork of the Roaring Branch where chainsaws will be used to directionally fell and position trees from the adjacent streamside.
Location
Towns of Sunderland and Glastenbury
Project timeline
1
Scoping Start
12/21/2020
2
Decision
03/2021 (Estimated)
3
Implementation
10/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| South Fork of the Roaring Branch Stream Restoration | Decision Signed Date: 03/15/2021 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |