The project purpose is to mitigate impacts and degradation of a wetland complex that the trail currently runs through. This proposal also seeks to address the recent loss of access to a connector trail through private property.
Location
Town of Readsboro
Project timeline
1
Scoping Start
01/27/2021
2
Decision
11/2021 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Trail Management; Travel Management |
| Hoosac Ridge Trail Relocation | Decision Signed Date: 11/30/2021 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |