The purpose and need for this project is to respond to an application submitted by Green Mountain Power as part of an ongoing state-wide project to upgrade power lines to current standards and to provide more reliable service.
Location
Towns of Goshen and Bristol
Project timeline
1
Scoping Start
04/29/2021
2
Decision
05/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 2021 Green Mountain Power Reconstruction Permit | Decision Signed Date: 05/19/2021 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |