The proposed action would authorize three maple tapping operations which have requested forest product special use permits to begin or expand operations.
Location
Town of Lincoln
Project timeline
1
Scoping Start
06/01/2021
2
Comment Period
11/10/2022
3
Objection Period Start
12/16/2022
4
Decision
02/2023 (Estimated)
5
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| 2021 Maple Tapping Special Use Permits | Decision Signed Date: 02/07/2023 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |