This project would replace the deteriorating or failing water control structures at 8 ponds with new functional water control structures and associated plumbing. The ponds would then be dredged to reduce sediment levels.
Location
Towns of Lodi and Hector.
Project timeline
1
Scoping Start
01/03/2022
2
Decision
01/2022 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Water Control Structure Replacements | Decision Signed Date: 01/14/2022 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Hector Ranger District |
| Legal Land Description | Not Applicable |