This project would replace the West Hill bridge with a new structure meeting the load limit required for local and Forest Service needs.
Location
Town of Rochester.
Project timeline
1
Scoping Start
02/09/2022
2
Decision
03/2022 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| West Hill Road Bridge Replacement | Decision Signed Date: 03/15/2022 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |