Project timeline
1
Scoping Start
04/15/2022
2
Decision
09/2022 (Estimated)
3
Implementation
10/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Sugarbush Reverse Traverse Realignment and Snowmaking | Decision Signed Date: 09/02/2022 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Rochester Ranger District |
| Legal Land Description | Not Applicable |