Decision Memo Completed

Green Mountain Power - Peru Construction Permit

Green Mountain and Finger Lakes National Forests Bennington, Vermont Manchester Ranger District

This project would issue a SUP with a term of 5 years to Green Mountain Power, authorizing them to construct approximately 3,120 feet of underground powerline, five junction boxes, and 1,080 feet of new above-ground line.

Location

Town of Peru

Project timeline

1
Scoping Start
09/13/2022
2
Decision
10/2022 (Estimated)
3
Implementation
11/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Green Mountain Power - Peru Construction PermitDecision Signed Date: 10/24/2022