Decision Memo Completed

Mount Snow High Traverse Widening

Green Mountain and Finger Lakes National Forests Windham, Vermont Manchester Ranger District

Widen the High Traverse alpine ski trail to relieve congestion, replace 400 feet of buried power line along the trail and add a valve house in the same vicinity to improve snowmaking efficiency.

Location

Town of Dover

Project timeline

1
Scoping Start
05/15/2023
2
Decision
03/2024 (Estimated)
3
Implementation
04/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Mount Snow High Traverse WideningDecision Signed Date: 03/19/2024
ForestsGreen Mountain And Finger Lakes National Forests
DistrictsManchester Ranger District
Legal Land DescriptionNot Applicable
Special use management