Issuance of a special use permit with a term of two years, authorizing work on the existing right of way. Fourteen hardwood trees would be cut and left in place, and the entire length of the right of way would be resurfaced with crushed stone.
Location
Town of Chittenden
Project timeline
1
Scoping Start
05/22/2023
2
Decision
05/2024 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Clark Right of Way Reconstruction Special Use Permit | Decision Signed Date: 05/15/2024 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Middlebury Ranger District |
| Legal Land Description | Not Applicable |