Relocation of the Corridor 7 trail crossing of Vermont State Route 11/30 to improve safety and the relocation of a section of trail that is currently closed due to failing infrastructure with the goal of improving safety and the trail experience.
Location
Town of Winhall
Project timeline
1
Scoping Start
01/24/2024
2
Decision
03/2024 (Estimated)
3
Implementation
03/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Travel Management |
| Corridor 7 Trail Relocation of 11/30 Crossing | Decision Signed Date: 03/25/2024 |
| Forests | Green Mountain And Finger Lakes National Forests |
| Districts | Manchester Ranger District |
| Legal Land Description | Not Applicable |